Abstract
A well-known problem m scheduling theory is to execute n umt-lengthjobs subject to precedence constraints on two processors m mmunum fimsh time Previous algorithms begin by finding the transmve closure of the precedence dag and so use time O(mm(en, n261)). An O(e + ha(n)) algorithm is presented which Is based on the idea of a “highest-level-first” (HLF) schedule Such a schedule always executes nodes on the longest paths of the precedence dag An HLF schedule is guaranteed to be optimum and can be constructed efficiently. © 1982, ACM. All rights reserved.
Author supplied keywords
Cite
CITATION STYLE
Gabow, H. N. (1982). An Almost-Linear Algorithm for Two-Processor Scheduling. Journal of the ACM (JACM), 29(3), 766–780. https://doi.org/10.1145/322326.322335