Magnitude of Construction Cost and Schedule Overruns in Public Work Projects

  • Shrestha P
  • Burns L
  • Shields D
N/ACitations
Citations of this article
184Readers
Mendeley users who have this article in their library.

This article is free to access.

Abstract

This study analyzed 363 Clark County Department of Public Works (CCDPW) projects to determine construction cost and schedule overruns in various types and sizes of the projects. The sample projects were constructed from 1991 to 2008, with a total construction cost of $1.85 billion, equivalent to 2012 cost. A one-factor ANOVA test was conducted to determine whether construction cost and schedule overruns significantly varied based on types and sizes of the projects. The study showed that large, long-duration projects had significantly higher cost and schedule overruns than smaller, short-duration projects.

Cite

CITATION STYLE

APA

Shrestha, P. P., Burns, L. A., & Shields, D. R. (2013). Magnitude of Construction Cost and Schedule Overruns in Public Work Projects. Journal of Construction Engineering, 2013, 1–9. https://doi.org/10.1155/2013/935978

Register to see more suggestions

Mendeley helps you to discover research relevant for your work.

Already have an account?

Save time finding and organizing research with Mendeley

Sign up for free