Nuclear power plant construction scheduling problem with time restrictions: A particle swarm optimization approach

2Citations
Citations of this article
15Readers
Mendeley users who have this article in their library.

Abstract

In nuclear power plant construction scheduling, a project is generally defined by its dependent preparation time, the time required for construction, and its reactor installation time. The issues of multiple construction teams and multiple reactor installation teams are considered. In this paper, a hierarchical particle swarm optimization algorithm is proposed to solve the nuclear power plant construction scheduling problem and minimize the occurrence of projects failing to achieve deliverables within applicable due times and deadlines.

Cite

CITATION STYLE

APA

Chen, S. K., Ti, Y. W., & Tsai, K. Y. (2016). Nuclear power plant construction scheduling problem with time restrictions: A particle swarm optimization approach. Science and Technology of Nuclear Installations, 2016. https://doi.org/10.1155/2016/2150692

Register to see more suggestions

Mendeley helps you to discover research relevant for your work.

Already have an account?

Save time finding and organizing research with Mendeley

Sign up for free