Concurrent and sequential networks - implications for project management

1Citations
Citations of this article
4Readers
Mendeley users who have this article in their library.
Get full text

Abstract

Timely completion of projects is one of the essential goals of project management. The present authors have developed a probability-based explanation of the lateness phenomenon as it relates to network complexity. Concurrent activities within a network are greater determinants of the delay than are comparable sequential activities. The implications for project management are discussed. © 1986.

Cite

CITATION STYLE

APA

Smith, L. A., & Mills, J. (1986). Concurrent and sequential networks - implications for project management. Engineering Management International, 3(4), 279–282. https://doi.org/10.1016/0167-5419(86)90024-4