Germanium recovery from coal fly ash by hydrometallurgical procedures was studied at the pilot scale (5 kg of fly ash/h). Results were used to design the equipment of a demonstration-sized plant (200 kg of fly ash/h). The process is based on hydrometallurgical operations: firstly a germanium extraction from fly ash by leaching and a consequent Ge separation from the other elements present in the solution by solvent extraction procedures. Based on the experimental results, mass balances and McCabe-Thiele diagrams were applied to determine the number of steps of the solvent extraction stage. Different arrangements have been studied and a countercurrent process with three steps in extraction and six steps in elution was defined. A residence time of 5 min was fixed in both the extraction and elution stages. Volumetric ratios in extraction and stripping were: aqueous phase/organic phase = 5 and organic phase/stripping phase = 5, so a concentration factor of 25 is achieved. Mixers and decanters were completely defined. The maximum extracted and eluted germanium was estimated and a global efficiency of 94% was achieved. The cost-effectiveness of the equipment was estimated using the Lang factors.
CITATION STYLE
Arroyo, F., Fernández-Pereira, C., & Bermejo, P. (2015). Demonstration plant equipment design and scale-up from pilot plant of a leaching and solvent extraction process. Minerals, 5(2), 298–313. https://doi.org/10.3390/min5020298
Mendeley helps you to discover research relevant for your work.