Takt Planning and Takt Control (TPTC) as a method for construction has the potential to reduce construction time in relation to normal scheduling without the increase of manpower. This leads to the question: what changes with the use of Takt planning? One theory is that Takt planning is using buffers more effectively than other schedule and planning methods. This paper provides an overview of the various buffers in Takt planning and describes how they can be used.
CITATION STYLE
Dlouhy, J., Binninger, M., & Haghsheno, S. (2019). Buffer management in takt planning - An overview of buffers in takt systems. In 27th Annual Conference of the International Group for Lean Construction, IGLC 2019 (pp. 429–439). The International Group for Lean Construction. https://doi.org/10.24928/2019/0226