Specific to dynamic adjustment of initial scheduling of virtual cell with new task insertion, we use Bayesian network to detect resource conflict process which may appear in virtual cell due to contention of production tasks on finite resources within specified time period, and then adopt critical chain method to resolute resource conflict based on priority of virtual cell and priority of process. At last, the feasibility and effectiveness of proposed methods through case study are verified.
CITATION STYLE
Han, W., & Tong, D. (2015). Research on Detection and Resolution of Resource Conflict of Virtual Cell Considering New Task Insertion. In MATEC Web of Conferences (Vol. 22). EDP Sciences. https://doi.org/10.1051/matecconf/20152201046