This paper describes the commissioning of the new water line (NWL) of the Central wastewater treatment plant in Prague and also the gradual reduction of the existing water line (EWL) loading. Concerning the NWL, the gradual start-up of the process without inoculation will be described. As to the EWL, the presentation describes the adaptation of the EWL operation to the relatively quick reduction of loading to approximately 35%.
CITATION STYLE
Wanner, J., Rosický, J., Kovařík, J., Srb, M., Lánský, M., & Sýkora, P. (2021). Commissioning of the new water line of the Central wastewater treatment plant in Prague and its impact on the operation of the existing water line. Water Science and Technology, 84(2), 293–301. https://doi.org/10.2166/wst.2020.575