Improving workflow and resource usage in construction schedules through location-based management system (LBMS)

35Citations
Citations of this article
152Readers
Mendeley users who have this article in their library.

This article is free to access.

Abstract

Critical Path Method (CPM), a planning and controlling technique, is widely used in the construction industry. However, CPM is criticized for its lack of workflow and inability to schedule continuous resource usage. Location-Based Management System (LBMS) fill these gaps and has been implemented in many construction projects. We propose that LBMS will improve schedules and project performance, addressing CPM’s main shortcomings. This study is composed of three case studies. CPM schedules were analyzed and were improved using LBMS tools. The resulting schedules show improved workflows, crew balancing, resource usage and had fewer interruptions, without affecting project duration. Furthermore, LBMS schedules were optimized with only a few scheduling operations and fewer planning elements. The computational benefit of LBMS increases with the number of locations and tasks in a schedule. Project managers will benefit from a simpler scheduling process and better resource flow.

References Powered by Scopus

Critical-path planning and scheduling

485Citations
N/AReaders
Get full text

Optimization of resource allocation and leveling using genetic algorithms

356Citations
N/AReaders
Get full text

Scheduling projects with repeating activities

245Citations
N/AReaders
Get full text

Cited by Powered by Scopus

Survey Comparing Critical Path Method, Last Planner System, and Location-Based Techniques

44Citations
N/AReaders
Get full text

How takt production contributes to construction production flow: a theoretical model

27Citations
N/AReaders
Get full text

Quantitative assessment of the impacts of BIM and lean on process and operations flow in construction projects

26Citations
N/AReaders
Get full text

Register to see more suggestions

Mendeley helps you to discover research relevant for your work.

Already have an account?

Cite

CITATION STYLE

APA

Olivieri, H., Seppänen, O., & Denis Granja, A. (2018). Improving workflow and resource usage in construction schedules through location-based management system (LBMS). Construction Management and Economics, 36(2), 109–124. https://doi.org/10.1080/01446193.2017.1410561

Readers over time

‘18‘19‘20‘21‘22‘23‘24‘25010203040

Readers' Seniority

Tooltip

PhD / Post grad / Masters / Doc 55

75%

Professor / Associate Prof. 8

11%

Researcher 7

10%

Lecturer / Post doc 3

4%

Readers' Discipline

Tooltip

Engineering 73

83%

Business, Management and Accounting 11

13%

Computer Science 3

3%

Nursing and Health Professions 1

1%

Save time finding and organizing research with Mendeley

Sign up for free
0