Abstract

The construction of the stellarator fusion experiment Wendelstein 7-X (W7-X) was accomplished in 2014. Commissioning of cryogenic system, first cool down of W7-X cryostat and operation of the magnet system was achieved. First plasma operation was accomplished 10th of December 2015. W7-X consists of a magnet system with 70 superconducting coils inside a cryostat. The cold mass of 456 tons is cooled with a helium plant with an equivalent refrigeration power of 7 kW at 4.5 K. The paper presents the commissioning of the cryogenic system, the cool down of the cryostat and first steady state operation with currents up to 12.8 kA. Helium temperatures, mass flow rates and pressure drops inside W7-X cooling circuits are as expected allowing safe magnet operation. Heat loads on the thermal shield and on the superconducting coils are lower than specified for the cryostat design.

Cite

CITATION STYLE

APA

Nagel, M., Dhard, C. P., Bau, H., Bosch, H. S., Meyer, U., Raatz, S., … Rummel, T. (2017). Cryogenic commissioning, cool down and first magnet operation of Wendelstein 7-X. In IOP Conference Series: Materials Science and Engineering (Vol. 171). Institute of Physics Publishing. https://doi.org/10.1088/1757-899X/171/1/012050

Register to see more suggestions

Mendeley helps you to discover research relevant for your work.

Already have an account?

Save time finding and organizing research with Mendeley

Sign up for free