Abstract
For the general case it is possible to determine a reasonable estimate of the economic sacrifice incurred when a larger connection than required is used. The focus of this paper is the extent of this economic sacrifice. For simplicity, a standard configuration of the double-angle connection is considered in which only n, the number of bolt rows (and, consequently, the length of the angles), varies. Based on values of n from 2 to 10, the cost of these standard connections is estimated. Ranges of n compatible with each beam size group are identified, and the percent increase in cost which results when a larger connection then required is used is then determined over these ranges.
Cite
CITATION STYLE
Carter, C. J., & Geschwindner, L. F. (1993). Economic impact of overspecifying simple connections. Engineering Journal, 30(1), 34–36. https://doi.org/10.62913/engj.v30i1.603