Abstract
A pigging stall occurred in a 5.9 km, 16-inch offshore gas pipeline, connecting an offshore platform to a Floating Storage Offloading Unit (FSO), due to insufficient platform pressure (~60 psig). The stalled pigging operation halted production and created significant operational inefficiencies. The aim of this study was to determine the minimum pressure required to prevent further pig stalls. A detailed flow assurance analysis, using multiphase transient modeling, identified that the optimal launching pressure to ensure pigging continuity was between 78-80 psig. Following these recommendations, field trials were conducted, successfully eliminating the stall and restoring pipeline functionality. These findings underscore the critical role of pressure optimization in pigging operations and highlight the effectiveness of flow assurance methodologies in mitigating operational risks and ensuring uninterrupted production.
Author supplied keywords
Cite
CITATION STYLE
Rizki, M. N., Putra, R. M., Ridho, M. R., Kosasi, D. C., Fadly, E., Safii, E. A., & Mujiburochman, M. (2025). Resolving Pigging Stalls in Low-Pressure Offshore Gas Pipelines: A Case Study on Pressure Optimization at Offshore Southeast Sumatra, Indonesia. In E3S Web of Conferences (Vol. 621). EDP Sciences. https://doi.org/10.1051/e3sconf/202562103009
Register to see more suggestions
Mendeley helps you to discover research relevant for your work.