The Multimode Resource-Constrained Project Scheduling Problem for Repetitive Activities in Construction Projects

66Citations
Citations of this article
80Readers
Mendeley users who have this article in their library.

This article is free to access.

Abstract

In construction projects, resource availability might limit the implementation of ideal schedules. Especially, when repetitive activities are involved, traditional resource-constrained project scheduling problem (RCPSP) models fail to allocate the resource consumption in an efficient manner. Besides, actual models only provide local optimal solutions and do not incorporate activity acceleration routines. To fulfill this gap, partially, a mathematical optimization model, the multimode RCPSP for repetitive activities in construction projects, is proposed and solved to optimality; it takes into account acceleration routines under real construction scenarios using spreadsheets. The article shows a complete computational experimentation over a real construction project, considering several scenarios of resource availabilities and continuity conditions. The model allows analyzing the resources efficiency indexes comparing them to resource consumptions, continuity of activities, and objective functions that reveal that fragmented activities do not provide better resource efficiency outcomes.

Cite

CITATION STYLE

APA

García-Nieves, J. D., Ponz-Tienda, J. L., Salcedo-Bernal, A., & Pellicer, E. (2018). The Multimode Resource-Constrained Project Scheduling Problem for Repetitive Activities in Construction Projects. Computer-Aided Civil and Infrastructure Engineering, 33(8), 655–671. https://doi.org/10.1111/mice.12356

Register to see more suggestions

Mendeley helps you to discover research relevant for your work.

Already have an account?

Save time finding and organizing research with Mendeley

Sign up for free