A CNPVaR-NPV Trade-off Model for Resource-Constrained Project Scheduling Problem Under Random Environment

0Citations
Citations of this article
6Readers
Mendeley users who have this article in their library.

Abstract

Projects face various risks and opportunities throughout their lifecycle. Integrating risk management into the project progression is a crucial factor for project success and an essential component of project management. This paper aims to evaluate the trade-off between Conditional Net Present Value at Risk (CNPVaR) and Net Present Value (NPV) in a stochastic environment. By assuming the activity duration and cash flow as random variables and setting activity start and execution modes as decision variables, a CNPVaR-NPV trade-off model is established with the objectives of minimizing CNPVaR and maximizing NPV, under priority relationships, execution mode, resource supply, and deadlines constraints. Based on the characteristics of the model, an algorithm combining nondominated sorting genetic algorithm II and Monte Carlo simulation is designed. The HVAC system project of Dongguan Jinyun Digital Park 5# Building is used as a case study to illustrate the effectiveness of the model and the algorithm. The results show that considering the CNPVaRNPV trade-off model can effectively mitigate potential risks and reduce project losses.

Cite

CITATION STYLE

APA

Zhang, Q., Teh, S. Y., & Cheang, P. Y. S. (2024). A CNPVaR-NPV Trade-off Model for Resource-Constrained Project Scheduling Problem Under Random Environment. International Journal of Electrical and Electronic Engineering and Telecommunications, 13(6), 478–485. https://doi.org/10.18178/IJEETC.13.6.478-485

Register to see more suggestions

Mendeley helps you to discover research relevant for your work.

Already have an account?

Save time finding and organizing research with Mendeley

Sign up for free